DETAILED ENGINEERING DESIGN

The 2nd stage of a solar project is the Detailed Engineering design, which is a continuation from Pre-Feasibility Analysis. Once the project is confirmed and the initial 5 documents submitted during the Pre-Feasibility stage is accepted by the client, along with the changes, we move to this stage.

 

Some of the Additional Documents, along with the other documents from Pre-Feasibility stage processed are

 

 

 

 

 

 

 

 

These documents enable the project team to purchase the necessary BOS, install and commission the plant.

 

 

 

Detailed Engineering.png

Timeline: 

  • Electrical Drawing Submission: 1 Week from project confirmation

  • Structural & Civil: 2 Weeks from project confirmation

  • Other Documents: 2 Weeks from project confirmation

  • As Built Drawings: 1 Week after commissioning